EL ZEINY GROUP
For Road Construction
LATEST PROJECTS
SHARM EL SHEIKH ROAD
Construction of 224 km freeway including earthworks, base Course layers (40 cm thickness with 15.40 M width/direction) and 2 Asphalt layers with 13.90 M width (binder thickness is 6 cm and wearing surface thickness is 5 cm.
project is 3 lanes both directions. Earthwork: 25,582,000 M3; Asphalt : 12,454,400 M2.
From 26 oct.2016 To 24 feb.2019.
WADI EL NATROUN EL ALAMEIN ROAD
Upgrade of wadi elnatron-elalamin road (sector 1) with a total length of 45KM. works include removal of existing asphalt and new construction of an extra lane to give 3 lanes on each side,
including excavation and backfill – base course and flood protection & pavement works – concrete barriers & slabs and guidance signs.
From 6 Jun.2014 To 24 March.2017
BENI SWEEF - EL ZAAFARANA ROAD
Rod El-Farag axis is a new construction road with total length of 29 km for its first phase which links Cairo Alex. Desert road and ring road.
ORC sections length is 29 KM. it consists of 4 lanes for cars and 1 bus lane for each direction.
From 12 Dec.2013 To 24 Dec.2017
WEST CAIRO MILITARY AIRPORT
Scope includes removal of asphalt layers, expansion of the main runway and construction of a new runway – The works include:
- Cut and removal of asphalt layers.
- Cracking of concrete slabs-sub-base course.
- Site leveling.
- Base course.
- Asphalt layers.
From 14 Jan.2015 To 24 Jun.2017
EL MELTZ MILITARY AIRPORT
Scope includes removal of asphalt layers, expansion of the main runway and
construction of a new runway. Phase 1 main quantities:
- CUT and removal of asphalt layers 282.000 m2 - Cracking of concrete slabs 65.000 m2
- Base course 25 cm thick 330.000 m2 - Site levelling 410.000 m2
- Sub – base course 440.000 m2
- Asphalt layers 1.200.000 m2 phase 1 (upgrading militartaxiway & aprone)
From 24 March. 2014 To 24 Oct.2017
ROD EL FARAG
ROAD
Rod El-Farag axis is a new construction road with total length of 29 km for its first phase which links Cairo Alex. Desert road and ring road. ORC sections length is 29 KM. it consists of 4 lanes for cars and 1 bus lane for each direction.
From 12 Dec.2013 To 24 Dec.2017
FAYOUM RING ROAD
Fayoum project is a 28 km road – part of the new construction regional ring road. It links Cairo ELfayoum desert road and Elwahat El Bahareya – Al Giza road, it consists of 4 lanes for each direction
From 1 Dec.2013 To 24 Jun.2015
HURGHADA INTERNATIONAL AIR PORT DEVELOPMENT
Construction of a new complete airfield composing of a runway of 4 Kim length & 75 M width, main taxiway of 4 KM length and connecting taxiways of category 1 with airfield lighting. Power supply and storm water drainage system works also include upograding75 M width.
From 14 Jun.2013 To 28 Jan.2015
CAIRO / ALEX DESERT ROAD UPDRADE
Upgrading the existing road into free highway, through 2 double level u turns and 2
high level bridges, and adding service road on both sides of the existingkm 126-km 160, Cairo / Alexs desert road; 36 km ; 20 m width project engineer: ibrenza – mamdouh hamaza.
From 6 May.2009 To 30 Oct.2013
EL MENIA ASSUIT ROAD
Create a new road from el Menia to Assuit road. Total length 90 KM – width 14.5 M. divided into section. Quantities: excavation 150,000 M3; backfill 6 million M3; Base 2,100 thousand M2, asphalt 1,932 thousand M2. For road sections 0-25 KM & 74 to 89 KM; Quantities included macadam layer of 360 thousand M2, binder layer of 360 thousand m2 and surface layer of 4.5 thousand M2 for each section.
From 9 Aug.2009 To 6 Jul.2015
AIN EL SOKHNA – EL KORIMAT ROAD
The work included planning and construction of a new highway road to replace the old serpent road.
Road TO REPLACE THE OLD SERPANT ROAD.
ROAD LEGHTH 90 km, WIDTH 2 x 14m, QUANTITY OF EXCAVATION 2,5000,000 m3 INCLUDING 480,000 m3 HARD Rock. Backfill 4,300,000M3.
From 1 Oct.2002 To 1 Aug.2004